The ICTWAY 2003 project is planned to be implemented during 24 months. The planned outcomes, milestones and deliverables are presented in a concentrated form in the table below. We presented each activity, sub-activity with the own indicators.

ACTIVITY
MILESTONE
DELIVERABLES
O.1. Assessment of the current ICT in Romania
Interviews with key persons
- 30 interviews planned - Copies of the interviews (questionnaires)
O.2. Analysis / benchmark study and follow-up visits
Study carrying out
Follow-up visits
- Study delivered
- 3 visits in place
- Copy of the study
- Copy of the TIG report 01
- Copy of the TIG report 02
O.3. Training on the commercialization process
Training on local area  - Training hand-outs
- Introduction
- How to prepare a TOC
- Sample Quicklook
- Weed Control
- Financing University
- References
- List of participants
- Photos
 A. Improving the communication structures
A.1. Up-grading the existing LANs - LAN system operational in Business Incubator Baia Mare
- LAN system operational in BIC Harghita
- LAN system operational in CBE Bucharest
- Copies of the acquisition documents
- Minutes for delivering and reception
A.2. Up-grading the software for existing LANs - Software solutions in place in BIC Baia Mare
- Software solutions in place in BIC Harghita
- Software solutions in place in CBE Bucharest
- Copies of the acquisition documents
- Minutes for delivering and reception
B. Develop the Training Program
B.1. Trainers selection - Minimum 10 trainers selected for the
project and appointed
- CVs of trainers
- Minutes of selection
B.2. Sharing experience with US similar organizations - 10 Romanian trainers participated at the sharing experience meetings
- Minimum 15 relevant organizations were visited
- Copies of the meeting minutes
- List of visited organizations
- List of participants
- Visit in USA 01 (Photos)
- Visit in USA 02 (Photos)
B.3. Training for trainers in ICT solutions development - 5 training sessions were organized focused on the mentioned topics
- Minimum 10 participants to the training for trainers
- Minimum 10 trainer were graduated in ICT technologies for SMEs
- Training hand-outs
- List of participants
- Copies of the training certificates
C. Develop the curriculum
C.1. Training manual and methodology for SMEs preparing - The training manual is printed on paper and on CD-ROM (Romanian and English languages)
- The training manual is available on Internet
- Copies of the training manual
- Copies of the CD-ROM
D. Implement the training for SMEs
D.1. Beneficiary companies selection
- Minimum 30 participants were selected as beneficiaries of the training on ICT for SMEs
- List of selected persons
- Minutes of the selection meeting
D.2. Training for SMEs delivering
- 3 training series were organized (2 in Baia Mare and 1 in Miercurea Ciuc)
- Minimum 30 participants joined the training on ICT for SMEs
- Minimum 30 participants were graduated on ICT for SMEs
- Training hand-outs
- List of participants
- Copies of the training certificates
- Photos
E . Provide ongoing assistance for SMEs
E.1. Assistance for ICT solution implementation
- Minimum 30 companies were assisted in-house for ICT solutions implementing
- Minimum 300 man-day were allocated for in-house assistance by the ICTWAY 2003 project staff
- Records of the assisted companies
- Reports of the advisors
E.2. Progress evaluation - Progress evaluation data base is operational
- Minimum 30 companies recorded and monitored
- Minimum 60 progress reports recorded to the project office
- Copies of the entrees of the project data base
E.3. Business start-up support - Minimum 5 companies were selected and introduced in the start-up program
- Minimum 50 man-days assistance for business start-up
- Selection documents (copies of the applications)
- Selection meeting minute
F. Linkages with other organizations
F.1. Networking for project partner organizations
- 200 records on the data base
- 200 destinations for messages
- 4 conferences delivered
- 12 seminars delivered
- Meeting documents
- Lists of participants
F.2. Networking for beneficiary SMEs - 3 workshops delivered for representative SMEs
- 3 workshops delivered for business associations and chambers of commerce
- Meeting documents
- Lists of participants
G. Dissemination of project outcomes
G.1. Dissemination via INTERNET
- ICTWAY 2003 project web site operational
- ICTWAY 2003 project web site visible and accessible
- Site home page and main pages in copy
G.2. Workshops for project dissemination - 3 workshops delivered for representative organizations - Meeting documents
- Lists of participants
H. Project management
H.1. Current project management delivering
- Project implementation in accordance with the grant contract
- Administrative documents (in copies)
- Financial documents (copies)
- Partnership agreements (copies)
H.2. International steering meetings - 5 steering committee meetings in place
- Meeting documents
- Lists of participants
- Meeting minute
H.3. Interim evaluation - 3 meetings for interim evaluation in place
- long term business plan for Business Incubator Centre
- Inception phase report
- First quarter report
- Six month report
- Third quarter report
- Mid-term report
- Fifth quarter report
- Seventh quarter report
H.4. Final evaluation - Impact study carried out by the project staff
- Project evaluation meeting in place
- Copy of the impact study
- Final report